Government Municipality Covid-19 Pandemic Camp Construction

Loss Event: Covid-19 Pandemic

Project Overview: Due to Louisiana’s rising cases of COVID-19, there were concerns that a large portion of their population would not be able to practice social distancing due to their living arrangements. Louisiana needed to create an area where people that were symptomatic could isolate away from family while awaiting their test results. Cotton was called on to design and build a 265-bed camp where these individuals could successfully isolate, without sacrificing comfort. Cotton Logistics worked around the clock to transport and construct an entire camp in 16 days. Despite challenges that arose during the construction phase, such as a change of location, a redesign of the buildings’ entrances, and an additional request for ADA accessible units, Cotton Logistics was still able to meet the original deadline.

Turnkey Services Provided:

  • Rapidly deployed personnel, assets, and equipment to the initial site
  • Deconstructed and mobilized assets to new location in a single day
  • Curated and installed ADA accessible facilities
  • Constructed a camp community with accommodations for 265 people
  • Installed fencing around the community
  • Redesigned the entrance to each building
  • Constructed thousands of square feet of decking between housing units
  • Installed electrical, sewage, and water infrastructure for each room
  • Provided WiFi and satellite TV to all of the buildings
  • Worked closely with the state’s health officials to ensure the camp met all of the requirements
  • Communicated daily with State and Local officials to ensure buildings complied with local regulations
  • Provided 24/7 on-site HSE support
  • Demobilized infrastructure and returned area to its previous state at the end of the project

The Cotton Differentiator: 

  • Constructed 265-bed community in SIXTEEN DAYS
  • Completed project ON TIME despite last-minute updates to project requirements
  • RELIABLE NETWORK of subcontractors helped speed up the process
  • Provided a CUSTOMIZED TURNKEY SOLUTION for client’s specific need
  • Followed SAFETY PROTOCOLS & REGUALTIONS during a global pandemic